Migrate legacy data
1. Introduction
Migrating legacy data is the project activity of preparing historical civil registration records for use in OpenCRVS. It includes deciding which sources are in scope, what legal status they have, how fields and identifiers will map, how exceptions will be handled, and how the migration will be tested and signed off.
For the functional capability, see Data migration. For technical implementation guidance, see Legacy data migration.
2. Source assessment
For each legacy source, document:
Source owner
Who owns the data and can approve migration decisions?
Legal status
Is this a legal civil register, notification source, index, statistics dataset, or supporting evidence?
Event coverage
Which event types are included?
Date range and volume
What period and how many records are covered?
Field coverage
Which mandatory OpenCRVS fields are present or missing?
Identifiers
What registration numbers, book/page references, PINs/UINs, National IDs, or legacy IDs exist?
Locations
Can places of event and registration be mapped to configured locations?
Attachments
Are scanned documents or evidence files available?
Amendments
Are corrections, name changes, adoptions, or other amendments represented?
Data quality
What duplicate, missing, inconsistent, or implausible data is known?
Access constraints
Are there technical, legal, privacy, or vendor constraints on extraction?
Migration decision
Migrate, migrate for review, quarantine, retain legacy access, or exclude?
3. Target status decision
The registration authority should approve the target status for each source before migration is built or tested.
Legally completed civil registration record
Import as Registered, if the source is confirmed as legally authoritative.
Incomplete record requiring staff review
Import as Declared or Notified, depending on completeness and workflow design.
Health notification, hospital spreadsheet, or local notification list
Use for reconciliation, duplicate checking, or import as Notified only if approved. Do not import as Registered unless legally accepted as a completed registration.
Uncertain, conflicting, or low-quality record
Quarantine, report as an exception, or retain in controlled legacy access until resolved.
Source outside migration scope
Do not migrate; document the reason and how staff can access it if needed.
Target status may vary by source, event type, date range, location, or data-quality band. This is a business decision, not a technical one.
4. Mapping sign-off
Before technical migration starts, sign off:
field-by-field mapping to the configured OpenCRVS event model
mandatory-field handling
registration number policy
legacy ID and source record ID handling
national ID or UIN handling
historical-to-current location mapping
attachment and source image handling
amendment and correction handling
unmapped fields and exclusion decisions
5. Data quality and exceptions
Agree which systematic errors may be corrected during transformation and which records require review. Migration should not rewrite legally meaningful historical facts without an approved correction policy.
Records that fail validation should have an owner, reason code, decision path and exception report. They should not be silently dropped.
6. Planning gates
A migration plan should normally include:
Source assessment approved.
Migration scope approved.
Field, identifier and location mapping signed off.
Test migration completed in a non-production environment.
Reconciliation and exception report signed off.
Cutover rehearsal completed.
Final load or delta load completed.
Post-load verification completed.
Controlled legacy access plan confirmed.
7. Pilot and cutover
The pilot sample should include clean records, messy records, duplicates, missing fields, old or renamed locations, records with amendments, records with attachments, and records used to print certificates.
The cutover plan should define data freeze timing, final delta migration, rollback or contingency arrangements, staff instructions for using legacy systems, and how late-arriving records are handled after go-live.
For low-connectivity settings, account for batch size, upload windows, support availability, service continuity, and whether records may be captured offline before synchronisation.